Compound rule of three

Machine translation

Around age 12 · Free

Learn

  1. Ellie bakes loaves of bread. With 2 ovens, working for 3 hours, she makes 60 loaves. How many loaves do 4 ovens make in 6 hours? The number of loaves depends on two quantities at once: the ovens and the hours.

    You solve it by changing one quantity at a time and keeping the other fixed. First the ovens change, from 2 to 4. With double the ovens, double the loaves: 60 × 2 = 120. Then the hours change, from 3 to 6. With double the hours, double the loaves: 120 × 2 = 240.

    Ovens244
    Hours336
    Loaves60120240
    One quantity at a time: first the ovens, then the hours
  2. At each step, look at whether the relationship is direct or inverse. If it is direct, you multiply by the scale factor. If it is inverse, you divide.

    Now with inverse relationships. 4 painters, working 8 hours a day, take 6 days to paint a wall. How many days do 8 painters take working 6 hours a day?

    Painters488
    Hours a day886
    Days634
    More painters: fewer days. Fewer hours a day: more days
  3. With double the painters it takes half the time: 6 ÷ 2 = 3 days. With 6 hours a day instead of 8 it takes longer: 3 × 8 ÷ 6 = 4 days. You can write it as a single calculation: 6 × 4 ÷ 8 × 8 ÷ 6 = 4.

    Careful. Do not add the changes together or multiply all the numbers. And do not treat every quantity as direct: some are inverse.

Worked examples

Example 1

Mara has 3 machines that make 90 packages in 2 hours. How many packages do 5 machines make in 4 hours, all at the same rate?

Machines355
Hours224
Packages90150300
  1. Machines: from 3 to 5, with the same time. More machines, more packages: 90 ÷ 3 × 5 = 150.
  2. Hours: from 2 to 4. More hours, more packages: 150 × 2 = 300.

They make 300 packages.

Watch out! Here many people multiply all the numbers, 90 × 5 × 4 = 1800, without thinking about how each quantity depends on the others.

Common mistake

Example 2

5 workers build 30 m of wall in 6 days. How many days do 10 workers take to build 20 m, all at the same rate?

Builders51010
Metres303020
Days632
  1. Workers: from 5 to 10, double. With more workers it takes less time: it is inverse. 6 ÷ 2 = 3 days.
  2. Metres: from 30 to 20. With less wall it takes less time: it is direct. 3 × 20 ÷ 30 = 2 days.

They take 2 days.

Watch out! Here many people treat the workers as a direct relationship and say that with more workers it takes longer.

Common mistake

Example 3

Vera uses 24 kg of feed with 4 pups in 3 days. How many kg do 6 pups use in 5 days?

Pups466
Days335
Feed (kg)243660
  1. Pups: from 4 to 6. More pups, more feed: 24 ÷ 4 × 6 = 36 kg.
  2. Days: from 3 to 5. More days, more feed: 36 ÷ 3 × 5 = 60 kg.

They use 60 kg of feed.

Watch out! Here many people forget the days and say 36 kg: they have only changed one quantity.

Common mistake

A challenge to think about

Think of a task that depends on two things, such as filling boxes with several people or watering the garden with several taps. Write down how long it takes with 1 and with 2 people and with different amounts of work. Make a table and work out which quantities are direct and which are inverse.

Practise

Rounds of 10 questions. Choose a level:

Your grade in this topic:No grade yetDo a round at the Basic level to get a grade.

Next topic: Proportionality graphs: a straight line through the origin; the gradient as the constant →